Thursday, February 25, 2010

Lynchburg OWDA LOANS

Just information. These are the OWDA Loans and not all the loans for the Village. They are for sewerage projects and water projects. You may view them online.

Here is a link http://www.owda.org/loantrk/LGALoans.asp?LGAID=533
Some of the early 1990 loans were a result of the plant. 7.96 is the
interest rate on the settlement of the original plant 1372 / 0621 is the
loan number.

Friday, July 10, 2009

Lynchburg Finances Looking Better








I'am happy to report that the Lynchburg Village Government is up to date on paying it's long term and short term debt. At the first of the month the first half of the years long term debt payment, for capital improvements on past water and sewer projects was payed totaling more than $80,000. After all operations and monthly invoices were payed, the fund balances were still in the black. They were very close, and money is still very tight, however it is looking like things are getting better. On the current course, I sincerely believe that monthly utility invoices on the local wastewater, sewer, should decrease drastically in the next 5 years.

The Council and myself discussed the EPA,s request to guarantee the upcoming long term debt for the phase one and two of the current capital improvements at the wastewater treatment facility. The Council did decide to start a process to assess certain properties affected by the upgrades. Many scenarios were looked at, for instances, not doing anything, adding the amount to the current monthly utilities invoice, pay off the debt,add an income tax, assessment to certain properties.

Burgess and Niple was chosen as the Engineering firm for phase two of the sewer plant project. This project is being fast tracked, due to the fact that Lynchburg will be receiving stimulus and other grant monies

The project plans for phase one and two are at the Municipal Building, along with the contracts, for anyone's review.

The Council passed the first comprehensive plan in the history of Lynchburg. This plan has been more than a year in the making. It is also available for review.

Saturday, June 20, 2009

Wastewater Treatment Phase I Online















Friday the June 13th, the pumps and headworks, which is phase one of the sewer plant upgrade, was brought online. It has worked for the last week and there have been no problems. Phase one will still continue throughout the next few weeks. The Engineer, Floyde Browne, has made a preliminary punch list. The contractor, Sunesis, will be wrapping the project up. I encourage the community to contact the office and take a tour of the Lynchburg water and sewer utilities. The utilities we operate are important to improve the quality of life within the community,improve property value, improve health; and the operations are regulated by the EPA, as well as many quality controls the certified operators maintain. Lynchburg has two licensed operators. Rick Ludwick and Mark Suitor, both have the proper certifications for water and wastewater (Sewer).
The wastwater plant, phase two will be fast tracked due to the money that Lynchburg will receive through stimulus funding process. The PTI, permit to install, has been approved by the Ohio EPA. In August, Lynchburg will be applying for additional 0% loans for the remaining balance. These loans will be through DEFA, which is the funding branch of the EPA. DEFA, will also be on sight throughout Phase II to assist Lynchurg, and make sure the project is being done properly. DEFA does this when the loan money, and when certain government grants are obtained. The balance of Phase II will be around one million dollars, after the 2.1 in grant money Lynchburg has received. It is imperative that the Council come up with a way that this will be paid back before the project is complete, or it will be added to the utility invoice in 2010. I do want to remind everyone that the sewer plant upgrade is mandated by EPA, this started in 1997, Lynchburg is under Findings and Orders (which is a legal binding document specifying environmental hazards caused by the current plant), the plant was overflowing and polluting the watershed, the plant was outdated, Lynchburg was fined, and this is a very important problem that deserves attention.