May 13, 2009
In response to questions regarding employment and business start up, I have came up with a list of contacts that may help. I encourage business and personal development in this area. I will assist anyone who is interested in opening a business or seeking additional training to provide for themselves and their families in the Lynchburg Area.
Sincerely,
Jeremy R. Shaffer
Highland County Chamber of Commerce
Katy Farber, Director 937-393-1111
Assistance with Business Plans, training, and development. SBA contact.
www.highlandcountychamber.com
Highland County Economic Development
Dan Cowdrey, Director 937-393-0339
Assistance with Government Funding and Strategic Planning within Highland County
Business Resource Center – Wilmington
Earl Gregory, Business Counselor 937-469-2058
Small Business Start Up, Career Training, Retraining, Seeking Employment, Retirement
www.backtoworkohio.com
Small Business Administration (SBA)
Bonnie Deer, 513-684-2814 X207
Assistance with Business Financing & Business Planning
Mondays on site 10AM-3PM National Bank & Trust
Southern State Community College Enterprise Center
Providing support, Tech assistance, and networking for entrepreneurs and business
937-695-9002 www.sscc.edu
The Ohio Small Business Development Center
Provides Confidential, free, in-depth business consulting
740-593-1797 www.southerncenter.ohio.edu
Appalachian Regional Entrepreneurship Group
Provides Customized consulting services to help start and grow business
740-593-1797 www.voinovichcenter.ohio.edu
SCORE
Service Corps of Retired Executives
Provides counselors to work with entrepreneurs and small business
513-684-2812 www.scoreworks.org/
Southern Ohio Procurement and Outreach Center
Provides help and assistance for business to sell to federal and state agencies
800-408-1334 www.sopoc.org
employment,
Showing posts with label workmanship. Show all posts
Showing posts with label workmanship. Show all posts
Wednesday, May 13, 2009
Tuesday, May 5, 2009
Wastewater Treatment Phase Progress Slowed Again
There have been a few hang ups throughout this small and short Phase One Project to build new head works at the Wastewater Treatment Plant. Each time something happens it move the schedule further off track. Currently the Project is thirty days off schedule. Since the Village is under Findings and Orders from the EPA, this is a cause for concern. The EPA has been notified, and does realize it is not due to fault of the Village of Lynchburg.
REcently, the on site resident representative was at the end of his contract. The resident rep. acts as the eyes and ears for the Engineer and the Village. He keeps record of progress, potential problems, and changes during the project. He is like an inspector. Since the time of the project was extended, the Public Works committee and myself believe it was necessary to have someone on sight to oversee daily activities. So he was extended through Floyd Browne for another few weeks at a reduced schedule. The resident rep. will be on site when work is happening.
Now, there seems to be a problem with the wrong specification of concrete poured in the project. A grade was used that did not contain a fiber reinforcement.The spec. book apparently called for reinforcement. This may slow the project since there is some disagreement with what to do to repair the issue. There are two options. First is two jackhammer the concrete and re pour it. Second would be to coat the current concrete with a formula that may prevent cracking. There has not been a decision made. I just want everyone to know the progress and assure them, that I will hold everyone to the schedule, keep the cost down, and only approve quality workmanship on this project. I have attached a couple emails below that may help everyone better understand the situation.
May 4th (1st Correspondence)
Mayor/Aaron. Attached is the reply from our structural engineer with respect to the lack of fiber reinforcement in the fillet walls at the screen structure. The bottom line is that there is no product that will totally eliminate the occurrence of shrinkage cracks in the concrete once it has been placed. The Xypex product submitted does meet wastewater plant applications and will provide an integral water proofing condition at the surface of the concrete which will certainly seal any cracks that have developed in the curing process to date. But the Xypex product will require a continued maintenance program, since shrinkage cracks can continue to form.
If Sunesis and the Village can agree upon an extended warranty of this condition past the one year warranty, the Xypex treatment if installed per the manufacturer’s strict specifications, could be considered as an alternative to the total removal and replacement of the fillet walls.
James J. Klamet
Director
Floyd Browne Group
MAy 4th (2nd Correspondence)
Mayor/Aaron,
The specification for the fillet concrete is clearly spelled out in section 03300. It may have required clarification in the form of an RFI prior to placement of the fillet concrete, but this was not initiated by Sunesis. Although the concrete placed is sufficient in strength and the proper air entrained admixture for freeze-thaw protection is present, the ability for shrinkage cracks will continue to persist. The surface treatments proposed will certainly protect against any adverse effects of current shrinkage cracks. There is still a high probability that future shrinkage cracks can develop. Hence, the need for an extended warranty and future re-application of this proposed product may be required.
It is our structural engineer’s opinion that the Xypex system is a product better suited for this application, but only used in conjunction with an extended warranty from Sunesis. We support our structural consultant’s recommendation only. Short of that recommendation, the existing fillet concrete must be removed and replaced to meet the plan specification.
James J. Klamet
Director
Floyd Browne Group
REcently, the on site resident representative was at the end of his contract. The resident rep. acts as the eyes and ears for the Engineer and the Village. He keeps record of progress, potential problems, and changes during the project. He is like an inspector. Since the time of the project was extended, the Public Works committee and myself believe it was necessary to have someone on sight to oversee daily activities. So he was extended through Floyd Browne for another few weeks at a reduced schedule. The resident rep. will be on site when work is happening.
Now, there seems to be a problem with the wrong specification of concrete poured in the project. A grade was used that did not contain a fiber reinforcement.The spec. book apparently called for reinforcement. This may slow the project since there is some disagreement with what to do to repair the issue. There are two options. First is two jackhammer the concrete and re pour it. Second would be to coat the current concrete with a formula that may prevent cracking. There has not been a decision made. I just want everyone to know the progress and assure them, that I will hold everyone to the schedule, keep the cost down, and only approve quality workmanship on this project. I have attached a couple emails below that may help everyone better understand the situation.
May 4th (1st Correspondence)
Mayor/Aaron. Attached is the reply from our structural engineer with respect to the lack of fiber reinforcement in the fillet walls at the screen structure. The bottom line is that there is no product that will totally eliminate the occurrence of shrinkage cracks in the concrete once it has been placed. The Xypex product submitted does meet wastewater plant applications and will provide an integral water proofing condition at the surface of the concrete which will certainly seal any cracks that have developed in the curing process to date. But the Xypex product will require a continued maintenance program, since shrinkage cracks can continue to form.
If Sunesis and the Village can agree upon an extended warranty of this condition past the one year warranty, the Xypex treatment if installed per the manufacturer’s strict specifications, could be considered as an alternative to the total removal and replacement of the fillet walls.
James J. Klamet
Director
Floyd Browne Group
MAy 4th (2nd Correspondence)
Mayor/Aaron,
The specification for the fillet concrete is clearly spelled out in section 03300. It may have required clarification in the form of an RFI prior to placement of the fillet concrete, but this was not initiated by Sunesis. Although the concrete placed is sufficient in strength and the proper air entrained admixture for freeze-thaw protection is present, the ability for shrinkage cracks will continue to persist. The surface treatments proposed will certainly protect against any adverse effects of current shrinkage cracks. There is still a high probability that future shrinkage cracks can develop. Hence, the need for an extended warranty and future re-application of this proposed product may be required.
It is our structural engineer’s opinion that the Xypex system is a product better suited for this application, but only used in conjunction with an extended warranty from Sunesis. We support our structural consultant’s recommendation only. Short of that recommendation, the existing fillet concrete must be removed and replaced to meet the plan specification.
James J. Klamet
Director
Floyd Browne Group
Labels:
concrete,
epa,
floyd browne,
Jeremy Shaffer,
lynchburg,
mayor,
ohio,
specification,
sunesis,
wastewater,
workmanship
Subscribe to:
Posts (Atom)